How to write business requirements developers can estimate

The business side had a list of requests, and the developers could not size them. What moved the demands forward in four working sessions.

Alexander KarlInterim and fractional product owner
5 min read
From an interim mandate, ordering platform
In short

A demand gets closer to an estimate when business and technical ownership are split inside one document, open questions are sorted by who has to answer them, and everything that several flows share is written only once. It needs a business owner who answers every week, because the structure does not replace those answers.

The situation

For the third release of an ordering platform the business side had a list of requests. The developers had no way to size them. In November we went through the demands line by line in four working sessions and compared them with the old system.

The platform is relevant for over 70 markets, and several teams build it. A demand that is unclear costs time in every one of them.

What a demand is here

The template has a simple test for whether something is a demand at all: can the stakeholder say “I want to ...” about it? A sentence about a service that has to run is not a demand, because no user would say it.

The template splits the ownership inside one document.

PartWritten by
Business needBusiness side
In scope and out of scopeBusiness side
DependenciesBusiness side
Open questionsTechnical product owner
High-level designTechnical product owner
Effort estimationTechnical product owner

The open questions are sorted by who has to answer them: business, design or technical. A demand passes four levels. The management overview only shows demands from the second level upward. A demand has an upper limit for its size, so a larger one has to be split. Every demand also needs a process model that matches its written flow.

A blocker that was a business rule

From an interim mandate, ordering platform

In the first session one technical question blocked everything: can a calculation step be mandatory? We restated it as a business requirement with a condition. The step is mandatory if the response comes within a set time. With that sentence the question was no longer a blocker at the first level. It became something to discuss at the second level.

Three demands became one base and two differences

From an interim mandate, ordering platform

On the same day we corrected the structure. Three demands for three order flows overlapped. Now one base demand carries everything they have in common, and the other two only describe the differences. Three days later the shared configuration moved into one central demand that the three flows refer to.

What we did not guess

From an interim mandate, ordering platform

In the second session there was a feature that nobody in the room could explain. We parked it for the business owner and did not write down an assumption.

In the fourth session a requirement was rejected because it applied to one order type only. A rule of thumb came out of that session: if something goes beyond what the old system does, ask where it comes from.

What slowed us down

In the third session we agreed that design work is not a precondition for moving a demand from the first to the second level. The deadline for clarifying feedback was moved from the end of the week to Wednesday.

After the four sessions the next step was with the business side. The open questions sorted to them have to be answered before an estimate can be filled in.

The structure makes a demand ready for an estimate. It does not replace the answers from the business side.

Where this has limits

This way of working fits when a business owner is available every week and an old system exists to compare against. I cannot say yet whether the estimates will hold, because the release is still being prepared.

In this mandate my role is measured on two numbers: how fast a demand gets from the first to the second level, and how many rounds of questions come after the second level.

What I would do differently

  • Ask for the answers from the business side earlier and with a fixed date. The deadline for feedback had to be pulled forward during the sessions.
Alexander KarlInterim and fractional product owner

I work as a product owner for companies that build digital products and online shops, for some months or for some days a month. The entries in this diary come from that work.

More entries in the diary
Fits this topic

Product Clarity Sprint

A short, fixed sprint that turns an unclear product question into a plan your team can build from.

Let’s talk about
your product

Book a 30-minute intro call and we’ll look at your product together.

Or call +49 157 53125112, or write to hi@alexanderkarl.com.

Or send me a message

I answer within 3 hours.

Lass uns über
Dein Produkt sprechen

Buch ein Kennenlernen von 30 Minuten, und wir schauen uns Dein Produkt gemeinsam an.

Oder ruf an unter +49 157 53125112, oder schreib an hi@alexanderkarl.com.

Oder schreib mir eine Nachricht

Ich antworte innerhalb von 3 Stunden.